How long does it take to install and test an automated car wash system

New Automatic car Wash

Setting up a new automatic car wash is one of the most exciting stages for anyone entering the car wash industry. Whether you are launching your first site or adding more locations to an existing business, understanding the installation timeline will help you plan budgets, staffing and opening dates with confidence.

Many first time owners are surprised to learn that installing and testing an automated car wash system is not just a case of lowering a machine into place and switching it on. There is a full process behind it and the timeline can vary quite a bit depending on the type of system you choose, how prepared the site is and whether you are installing extra features such as a self service car wash or a touchless car wash machine.

This guide walks you through the typical stages involved and explains how long each part usually takes. The aim is to give you a clear picture of what to expect, without confusing jargon or unnecessary technical detail.

Contact us Today

Understanding the different types of systems

Before looking at timelines, it helps to understand the kind of system you are choosing. An automatic car wash can mean anything from a traditional rollover style machine to a fully touchless car wash machine that works with sensors and high pressure water. Some businesses choose automatic car washing machines that focus on speed and high throughput, while others prefer a more detailed automatic car cleaning machine that produces a longer and more premium wash cycle.

There are also fully automated tunnels which require more groundwork, as well as compact auto car washer machines which are ideal for smaller sites. Brands such as Adriateh or Washworld each have their own installation approaches, but the general process is similar between manufacturers. The key thing to remember is that the more complex the system, the more time may be required for preparation and testing.

Book in Today

Step one: site preparation

This is usually the longest stage and can take anywhere from one week to several weeks depending on the starting condition of the site. If the site is already prepared with correct drainage, power supply and structural space, then preparation can be relatively fast. If the site needs fresh concrete, new drainage channels or substantial groundwork, then this part naturally takes longer.

Most sites need at least some preparation because washing car machines require proper drainage, electrical supply, water access and enough space for vehicles to move around safely. This part often includes pouring concrete, installing underground pipes, preparing the bay where the car wash machine will sit and ensuring that everything is level and secure. Weather can also affect this stage. For example, concrete needs to cure properly before installation can begin.

Step two: delivery and placement of the equipment

Once the site is ready, the automatic car wash machine or touchless car wash machines can be delivered. This stage is usually much quicker than people expect. Delivery and placement often take only a day or two. The equipment is positioned using specialist lifting gear and aligned carefully according to the manufacturer’s layout plans.

Some systems arrive in modular parts which are assembled on site, while others arrive as more complete units. Automatic car wash for sale listings often show neat, fully assembled machines, but in reality the installation team still needs to secure them, connect them and ensure the entire framework is set up correctly.

Step three: connecting the utilities

Even though the machine may be physically in place, it is not ready to run until everything is connected. This includes water supply, power, air lines and any chemical injection systems. The exact timeline depends on the machine type. A touchless car wash machine, for example, may require more precise pressure adjustments and sensor alignment. Tunnel systems with multiple components take longer, while single bay automatic car washing machines can be connected more quickly.

For most systems, this part of the process usually takes between two and four days. The installation team will follow the manufacturer guidelines closely and will check every connection carefully because even something small, such as a loose water line, can cause an issue during testing.

Step four: software setup and calibration

Modern automatic car wash machines are highly intelligent. They rely on software, sensors and programmed wash cycles to operate correctly. Once the physical installation is complete, the team will set up the software and ensure all the wash programmes are functioning as they should.

Calibration includes things like adjusting spray angles, setting brush pressures for non touch systems, programming wash cycle timings and checking that any payment or entry systems work smoothly. Even a self service car wash bay requires calibration to make sure customers get the correct timing and pressure for each selection.

This stage usually takes between one and three days depending on the level of automation and complexity.

Step five: testing the system

Testing is one of the most important steps in the entire process because it ensures the equipment runs smoothly before opening to the public. A full testing phase can take between two days and one week. The installation team will run multiple wash cycles, adjust the settings, check every function and look for anything that might cause issues once customers start using the system.

This usually includes testing bays for leaks, monitoring water pressure, checking all safety sensors and making sure the system can operate continuously without interruption. Touchless car wash machines in particular require precise sensor testing so that vehicles are detected correctly.

Step six: staff training and final checks

Even the most automated system requires some staff familiarity. Training usually takes a day or two, depending on the size of the team. Staff learn how to start cycles, stop cycles, manage the control panel, load chemicals, check water levels and handle basic maintenance. They also learn what to do if the system pauses or detects an error.

After training, the installation team completes a final inspection to confirm that everything is ready for launch. This includes verifying safety features, confirming the performance of the auto car washer machine and making sure all signage and flow directions are correct for customers.

Final thoughts

Installing an automated car wash system is a detailed but rewarding process. Although the timeline can vary, understanding each stage helps you plan with confidence and avoid surprises along the way. A well installed and properly tested system will always operate more reliably, which is why the preparation and testing phases are so important.